  • Jan 28, 2025
  • Troy Dualam Inc.

Planning a custom tank project? Explore our custom FRP tanks.

Installing an aboveground fiberglass reinforced plastic (FRP) tank is not a standard checklist applied to every vessel. The support, handling, anchorage, piping, venting, testing and commissioning requirements must match the approved tank design and the actual site.

Scope of this article: This article provides general educational information for aboveground FRP tank installations. It is not a lifting plan, installation procedure, foundation or anchorage design, or commissioning instruction. Buried, horizontal, field-fabricated, leg-supported, skirt-supported and saddle-supported tanks require different provisions. Applicable regulations, approved project documentation, design conditions and limits shown on the tank nameplate and in its documentation, the fabricator’s current written instructions, site-specific engineering requirements and applicable safety procedures must be met. If instructions conflict, stop the affected work and obtain a written resolution from the tank fabricator and the party responsible for the relevant design, according to their respective responsibilities, before continuing.

FRP tanks can provide a lightweight, corrosion-resistant storage solution when the resin, corrosion barrier, laminate construction, temperature and design conditions are matched to the actual chemical service.

General Planning Considerations for an Aboveground FRP Tank Installation

1. Confirm the approved project basis

Before mobilization, confirm the current approved drawings, equipment orientation, foundation and anchorage design, shipping and lifting instructions, nozzle schedule, pressure and vacuum ratings, piping interfaces, venting requirements, inspection plan and division of responsibilities. Do not use a generic installation detail in place of the fabricator’s current project documents.

2. Foundation and support for vertical flat-bottom FRP tanks

An aboveground vertical flat-bottom FRP tank designed for continuous bottom support requires complete and uniform support over the intended area, including the bottom edge, in accordance with the fabricator’s details. The foundation must be designed for the anticipated loading conditions, including the empty, full and test conditions, and applicable site loads, taking account of ground conditions and permissible settlement.

The supporting surface must be level, smooth, clean and free of projections, voids and debris. Bottom drains and nozzles must have the clearances and support details shown on the approved drawings, without leaving areas of the bottom unsupported where support is required or transmitting excessive loads to the connections. Other tank configurations require their own engineered support details.

When the foundation design or the fabricator’s current written instructions require bedding, support and leveling grout or a pad, use only the system specified for that tank, with the material, thickness, mechanical properties, chemical and environmental compatibility and support layout defined for the project. Do not substitute loose aggregate or an improvised pad.

If an elastomeric pad is specified, use the exact material, thickness, hardness, chemical and environmental compatibility and coverage arrangement approved for that tank. Do not improvise with a generic rubber sheet: excessive compressibility, joints between pieces, wrinkles, chemical attack or trapped debris can cause loss of support or damaging load concentrations.

3. Inspect, handle and secure the tank correctly

Before unloading, inspect the tank’s exterior and, from a safe position outside the tank, the accessible parts of its interior. Do not enter or climb onto the tank to perform this inspection. Document cracks, crazing, abrasion, impact damage, distortion and damage at nozzles, lugs or shipping supports. If damage is found, obtain the fabricator’s direction before unloading or moving the tank. Complete any remaining receiving inspection after the tank is safely unloaded and supported, following the applicable access and confined-space procedures. Do not place a damaged tank in service until its condition has been assessed and any required corrective work has been accepted by the responsible parties.

Move the tank only under an approved handling and lift plan, using the designated lifting lugs or a manufacturer-approved non-metallic sling and spreader arrangement. Never lift from nozzles, flanges, hold-down lugs or other fittings. Do not roll, drag or slide the tank, and do not allow chains, wire rope, hooks, fork tines or hard objects to contact the laminate. A forklift may be used only when the fabricator’s written instructions identify an approved pallet or support method. Secure the empty tank against wind, rolling, overturning and flotation until final anchorage is complete.

Do not walk, climb or stand on the tank roof, shell, nozzles or attachments unless the approved design identifies a surface or component as load-bearing access. If authorized internal entry is required, follow the site’s confined-space and lockout procedures and use clean soft-soled footwear, padded ladder feet and protective padding as specified. Soft-soled footwear does not replace required personal protective equipment or make an undesigned surface safe to walk on.

4. Install the engineered anchorage system

Anchorage is a project-specific engineered system. Install the anchors and associated hardware and secure the tank using its hold-down lugs in accordance with the approved foundation and anchorage drawings, accounting for applicable wind, seismic, flood, flotation and operating loads. Do not use anchors to drag the tank into position, force it level or close a gap beneath a hold-down lug by tightening.

Follow the fabricator’s specific written instructions and the approved project details for shimming, grouting, partial water filling and final tightening, when those operations are specified, without exceeding the specified tightening.

5. Keep nozzle loads within the specified limits

Set the tank to the orientation, elevation and plumbness shown on the approved drawings before connecting piping. Check that the nozzle locations match the installed piping, but never force a nozzle into alignment. Independently support piping, valves and accessories, and provide the flexibility defined by the project engineering for settlement, thermal movement and vibration so the forces and moments transmitted to the tank and its nozzles remain within the specified allowable limits. Use the gasket, mating-flange configuration, fasteners, tightening sequence and bolt torque specified for the connection.

6. Protect the tank from pressure and vacuum

Do not assume an atmospheric storage tank can tolerate imposed pressure or vacuum. Before filling, draining, pumping, cleaning or commissioning, verify that the permanent vent or vapour-handling path is not isolated or obstructed and is sized for the governing inflow, withdrawal, thermal and process cases. Confirm that all specified pressure-relief devices, vacuum-relief devices and operating interlocks are installed, configured according to the approved project documents and functional. Never operate the tank outside its stated internal- or external-pressure rating.

Blocked vents, fouled screens, rapid pump-out, rapid filling, cooling and steam condensation can create damaging pressure or vacuum. A blind flange is an isolation device, not pressure- or vacuum-protection equipment.

7. Inspect and commission against the project documents

A qualified person should inspect and document the tank’s condition on receipt and inspect it again after installation, before commissioning, in accordance with the approved drawings and the fabricator’s written instructions. Depending on the tank configuration and project requirements, the inspection should include bottom contact and support on the foundation; orientation and plumbness; laminate and corrosion-barrier or thermoplastic-liner condition, according to the construction; nozzles and flanges; hold-down-lug support and anchorage; piping and valve supports; connection flexibility; gaskets and fasteners; vent and overflow paths; pressure- or vacuum-protection devices; access and safety items; and the grounding, bonding or electrostatic-control measures required by the design. This does not mean that a conventional FRP tank is electrically conductive or can be grounded using a generic arrangement.

When the approved project documents or the fabricator’s written instructions specify a fill or leak test, complete it under the applicable procedure, with the fluid, level, sequence, duration and acceptance criteria defined. During filling, check from a safe position for settlement, unsupported areas, distortion or leakage; if an anomaly is detected, stop the test and obtain instructions before continuing. Resolve nonconformances and document acceptance by the responsible parties before placing the tank in service. Do not drill, modify or field-repair the tank without the fabricator’s written authorization and the specific applicable procedure, with the engineering review and regulatory requirements that apply. Any required entry for internal inspection must be performed under the site’s confined-space program.

Project information for foundation and support coordination

As initial information, gather the following data: the stored medium, concentrations, contaminants and solids; normal and abnormal temperatures, including cleaning where applicable; specific gravity; design pressure and vacuum; expected dimensions and fill levels; tank configuration, orientation and supports; nozzles and loads from piping and other connected equipment; location and site conditions, including applicable wind, seismic and flood conditions; containment arrangements; and project regulations and specifications. The tank fabricator and the foundation designer must define the additional information needed for their respective designs.

Foundation design belongs to the professional responsible for that project scope, with the qualifications required by local regulations. The tank fabricator supplies the equipment load data and support requirements within its scope. Responsibilities and interfaces must be defined in writing.

How Troy Dualam Supports a Tank Project

Troy Dualam Inc. designs and fabricates FRP and dual-laminate tanks and equipment. Troy Dualam Services Inc. is a separate company from Troy Dualam Inc. and offers field installation, inspection, repair, relining and outage support. Availability for the project location and the scope of these services must be expressly confirmed; another qualified provider may also be engaged.

The approved contractual and technical project documents must identify who is responsible for the foundation, rigging, anchorage, piping, testing and commissioning, and define the interfaces between the parties.