Custom fully buried FRP underground storage tanks, also called fiberglass underground storage tanks, require more than a material selection or a standard traffic-load label. The project-specific structural design basis must address the intended service and operating conditions, burial depth, soil and backfill properties, installation conditions, groundwater, applicable surface and vehicle loads, shell buckling and deflection, flotation resistance, and anchoring where required.
Troy Dualam approaches underground FRP tank work on a project-specific basis. The governing design basis, calculation methods, fabrication requirements, inspections and documentation must be identified for the actual service and site conditions before fabrication begins.
There Is No Single Universal Underground FRP Tank Code
An underground tank may draw on several recognized methods, but no one reference automatically covers the complete buried vessel and installation.
Depending on the project, the engineering basis may incorporate:
- buried flexible-structure methods from AWWA guidance, where technically applicable;
- AASHTO vehicle live loads for the applicable traffic condition;
- recognized ring-stiffness or load-deflection methods as supporting references, where technically applicable;
- project-specific checks for shell deflection, global and local buckling, end loading, buoyancy, flotation and anchoring;
- documented fabrication and laminate requirements;
- jurisdictional environmental, installation, inspection and monitoring requirements.
The adopted references and editions must be stated in the project documents. AWWA M45, AWWA C950 and common stiffness methods are principally pipe-focused; any adaptation to a tank must be technically justified and documented. A traffic-load designation, pipe-focused method or component calculation must not be presented as the complete tank design standard.
ASME RTP-1 Scope for a Fully Buried Tank
ASME RTP-1-2025 paragraph 1-120(g) explicitly excludes “fully buried underground closed vessels.” Accordingly, the complete tank must not be represented as designed, fabricated, certified or marked as conforming to ASME RTP-1.
Where technically applicable, selected RTP-1 provisions may be adopted as identified engineering, laminate-detail or fabrication criteria. Their use and limits must be documented. This does not make the complete tank RTP-1-compliant or eligible for RTP-1 marking.
Troy Dualam Inc. holds ASME RTP Certificate of Authorization No. RTP-51, limited to the authorized shop-fabrication scope stated on the certificate. Review the current certificate and approved scope.
HS-20 and HS-25 Are Traffic Loads, Not Tank Standards
AASHTO HS-20 and HS-25 are vehicle live-load designations or load cases used in the structural analysis of the buried system. They do not define the complete tank design, laminate, chemical compatibility, installation or quality requirements. Modern projects may specify HL-93 or another design live-load model instead.
The design must establish how the selected traffic load reaches the tank through the pavement, distribution slab, soil cover and backfill. The analysis must address burial depth, applicable impact and load factors, other surcharge loads, soil–structure interaction, tank stiffness, groundwater and governing load combinations. The project must identify the applicable code edition and jurisdictional requirements.
Underground FRP Tank Design Packet: Six Inputs to Resolve Before Fabrication
A useful inquiry is more than a capacity and an “HS-20” label. Organize the information below into one project-specific design packet. For each input, identify its source, revision and the party responsible for confirming it. Mark missing information as unresolved rather than replacing it with an assumption from another installation.
- Service and tank geometry. Provide the stored fluid or mixture, constituents and concentrations, normal and upset temperatures, operating and design pressure or vacuum, required capacity, dimensions, nozzles and access openings. Identify the empty, partly filled and full conditions the responsible engineer must consider. A tank’s internal service and its external buried loading must both be addressed.
- Burial, soil and backfill. Provide the burial depth, site and geotechnical information, native soil properties, bedding and backfill specification, and placement and compaction requirements. Identify who supplies and confirms these inputs. The tank structure and the specified surrounding materials must be evaluated together; “suitable for burial” is not a substitute for a defined installation.
- Groundwater and flotation restraint. State the design groundwater elevation and the applicable saturated conditions. Have the responsible engineer define the flotation load cases and any required hold-down arrangement, including how loads reach the tank through straps, deadmen, a slab or another restraint. Do not rely on an assumed liquid level to resist uplift without documenting that condition in the design basis.
- Surface and vehicle loading. Provide pavement or distribution-slab details, applicable vehicle load cases, other surcharges and the adopted reference editions. Document load distribution through the cover and backfill, applicable impact and load factors, and governing combinations. HS-20, HS-25 or HL-93 identifies a traffic-loading input—not the complete tank design or an automatic rating.
- Connections and installation interfaces. Identify connected piping loads, local nozzle and attachment loads, access constraints, handling conditions and installation sequence. Assign responsibility for the tank, excavation, bedding, anchoring, connections and inspections. Fabrication and site execution are separate scopes; they must agree on the same approved drawings and installation requirements.
- Acceptance and approval requirements. Identify the governing project criteria, calculations, fabrication and laminate requirements, applicable inspections and tests, documentation, and owner, engineer-of-record and authority approvals. State any required listing or certification for the exact complete tank and service. A listed component, a pipe-focused calculation method or selected RTP-1 provisions cannot establish conformity of the complete buried tank.
Use the packet as a review checklist, not an installation procedure. Ask which inputs remain open, who will resolve them and which drawings or calculations depend on them. Confirm the approved project-specific design and installation requirements before fabrication. If groundwater, burial depth, backfill, traffic or service conditions change, refer the change to the responsible engineer rather than carrying the earlier design forward unchanged.
Send Troy Dualam the design packet for a project-specific review. For shop-fabricated equipment outside this buried-tank scope, see Custom FRP Tanks & Vessels.
Shell Deflection, Buckling and End Loading
Buried composite shells interact with the surrounding soil and backfill. The design therefore evaluates more than internal capacity.
Project calculations may include:
- ring or shell stiffness;
- allowable deflection;
- global buckling;
- local buckling;
- end-cap or head loading;
- local loads at nozzles and attachments;
- handling and installation conditions;
- long-term load combinations identified by the responsible engineer.
The calculation method and acceptance criteria must be defined for the project rather than inferred from a general product claim.
Groundwater, Flotation and Anchoring
An empty or partly filled buried tank can be vulnerable to buoyancy when groundwater rises. The design must evaluate the applicable groundwater elevation and the stabilizing weight of the tank, contents, overburden and any concrete components.
Where required, a project-specific anchoring system may include engineered hold-down straps, deadmen, a base slab or another documented restraint arrangement. The tank and its anchoring system must be considered together; a generic statement that the tank is “anchored” is not enough.
Backfill and Installation Are Part of the System
Specified backfill and compaction support the buried shell. Incorrect material, uneven placement, uncontrolled compaction or an unapproved installation sequence can change the loads acting on the tank.
Project documents should define:
- excavation and foundation preparation;
- approved bedding and backfill materials;
- placement and compaction requirements;
- tank positioning and temporary restraint;
- hold-down and anchoring installation;
- connection and monitoring details;
- inspection points during burial;
- final documentation and acceptance.
Listings and Regulatory Requirements Must Be Project-Specific
No UL or ULC listing, NSF/ANSI certification, potable-water acceptance, petroleum-service approval or other third-party listing is implied by the use of FRP. Any such requirement must be identified at the outset and verified for the exact complete tank system and intended service. A listed or certified resin, liner or component does not establish a listing or certification for the complete tank.
Discuss an Underground FRP Tank Project
Troy Dualam can review custom fully buried FRP tank requirements when the intended service, tank geometry, site and geotechnical conditions, groundwater, installation and traffic loads, structural design criteria, and required owner, engineer-of-record and authority approvals are defined.
To start the review, provide the stored media, concentration, temperature, capacity, burial depth, soil and backfill information, groundwater conditions, surface loading, anchoring constraints and governing project requirements.
Contact Troy Dualam’s engineering team.
Frequently Asked Questions
Are fully buried FRP tanks designed to ASME RTP-1?
Not as a complete buried vessel. ASME RTP-1-2025 paragraph 1-120(g) excludes fully buried underground closed vessels. The complete tank must not be represented as designed, fabricated, certified or marked as conforming to RTP-1. Selected provisions may be adopted as identified criteria, but that does not make the complete tank RTP-1-compliant or eligible for RTP-1 marking.
Does an HS-20 rating define the complete tank design?
No. HS-20 is a vehicle live-load designation or load case. The design must also address load distribution, applicable impact and load factors, surcharge loads, soil–structure interaction, groundwater, shell stiffness, buckling, deflection, flotation, anchoring, installation and the required service conditions. Use “designed for the documented project-specific HS-20 load case” only when that basis has actually been established.
What information is required to evaluate an underground FRP tank?
The evaluation requires the stored media, concentration and temperature, capacity, dimensions, burial depth, soil properties, backfill and compaction, groundwater, pavement or slab, traffic loading, nozzles, connected loads, anchoring conditions, jurisdiction and required approvals.
Are underground FRP tanks automatically UL or ULC listed?
No. A required listing must be identified and confirmed for the exact complete tank system and service. FRP construction—or a listed resin, liner or component—does not establish a UL or ULC listing for the complete tank.
Why are flotation and anchoring calculations required?
Groundwater can create buoyancy when a buried tank is empty or partly filled. The project design must evaluate uplift and define any required straps, deadmen, slab or other restraint together with the tank structure.
This page covers underground FRP tanks. For custom shop-fabricated FRP and dual-laminate tanks, see Custom FRP Tanks & Vessels.